Deployment Scope

LMU/COICP Example

Deployment Scope Example

Define the LMU-COICP-RC-001 baseline, Internal Engineering Review Environment, approved LMU reviewer groups, Spring Semester Synthetic Incident Dataset, enabled capabilities, disabled capabilities, restrictions, and rationale.

ES-112 Scope LMU Review Environment

Example purpose

This artifact defines the deployment scope for LMU-COICP-RC-001.

The scope is intentionally narrow. It deploys the baseline for internal engineering review, not operational pilot.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner COICP Product Engineer
Primary reviewers COICP Product Owner, Campus Operations lead, IT security reviewer, Architecture Review Board chair, AI reviewer, Compliance reviewer
Status Accepted for internal engineering review deployment
Last updated 2026-07-06
Related Engineering Stage ES-112 — Deployment and Transition
Project workspace target docs/project-workspace/deployment/deployment_scope.md

Baseline

Field Value
Candidate LMU-COICP-RC-001
Source release decision docs/project-workspace/release/release_decision_record.md
Source operational decision docs/project-workspace/operations/operational_readiness_summary.md
Target environment LMU-COICP Internal Engineering Review Environment
Deployment ID DEP-LMU-COICP-2026-03-18-001
Operational pilot Not approved

Environment topology

Component Deployment Status Notes
COICP review application Enabled Internal review instance only
Synthetic incident store Enabled Loaded with Spring Semester Synthetic Incident Dataset
Evidence event store Enabled Normal-path evidence event observation
Mock directory service Enabled 24 synthetic reviewer accounts
Campus notification integration Stubbed No real notifications
Emergency workflow integration Disabled Existing emergency procedures remain authoritative
AI Incident Summary service Disabled Feature flag off; no UI control exposed
Production data connectors Disabled No production systems connected
Review telemetry log Enabled Used for ES-113 monitoring

Approved reviewer groups

Group Accounts Purpose
Campus Operations 5 Intake workflow and queue review
Facilities Coordination 3 Facilities handoff review
Residence Life 3 Residence-hall scenario review
Campus Safety Liaison 2 Emergency-boundary and prohibited-use review
Information Technology 4 Access and deployment control review
Compliance Office 2 Sample data and retention-boundary review
Architecture Review Board 4 Evidence and guardrail review
AI Review 1 AI-disabled status review
Total 24 Approved internal reviewers

Dataset

Field Value
Dataset name Spring Semester Synthetic Incident Dataset
Dataset ID LMU-COICP-SYN-SPRING-2026
Preloaded incidents 421
Synthetic buildings Damen Hall, Mertz Hall, Information Commons, Quinlan Hall, Centennial Forum, Norville Center
Real incident data None
Sensitive personal data None
Production data None

Enabled capabilities

  • Create synthetic incident record.
  • Review incident current state.
  • Generate evidence event on valid incident creation.
  • Exercise Campus Operations intake queue.
  • Exercise Facilities and Residence Life handoff scenarios.
  • Review emergency-boundary warning scenario.
  • Review access boundaries for approved reviewer accounts.
  • Record reviewer feedback.
  • Monitor evidence and guardrail behavior.

Disabled capabilities

  • AI Incident Summary.
  • Real campus incident intake.
  • Production data storage.
  • Emergency notification workflow.
  • Campus dispatch integration.
  • Post-incident export for real incidents.
  • Broad stakeholder access.
  • Student, faculty, public, or external access.

Deployment restrictions

  • Do not add users outside the approved reviewer list.
  • Do not enable AI Incident Summary.
  • Do not enter real incident data.
  • Do not connect production systems.
  • Do not treat the environment as operational.
  • Do not invite campus operators outside the reviewer group.
  • Stop deployment or review if real data, unauthorized access, AI activation, evidence failure, or emergency workflow misuse occurs.

Scope rationale

The baseline is mature enough for LMU internal engineering review but not mature enough for operational pilot.

The deployment scope preserves that distinction.