Requirements Review

LMU/COICP Example

Requirements Review Example

Record the LMU/COICP requirements review for LMU-COICP-REQ-001, including scenario coverage, findings, open issues, acceptance conditions, and concrete Planning handoff actions.

ES-102 Review Baseline Decision

Example purpose

This artifact records the ES-102 requirements review.

The review determines whether the requirements are concrete enough to support Planning and whether the business scenarios are realistic enough to flow through later stages.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner COICP Product Owner
Primary reviewers COICP Product Engineer, Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison, Facilities reviewer, Residence Life reviewer
Status Accepted with carried-forward actions
Last updated 2026-07-06
Related Engineering Stage ES-102 — Requirements and Constraints
Project workspace target docs/project-workspace/requirements/requirements_review.md

Requirements context

Field Value
Source vision package ES-101 — Vision and Problem Definition
Requirements baseline produced LMU-COICP-REQ-001
Planning baseline expected next LMU-COICP-PLAN-001
Architecture baseline expected later LMU-COICP-ARCH-001
Design baseline expected later LMU-COICP-DES-001
Implementation baseline expected later LMU-COICP-IMPL-001
Integrated baseline expected later LMU-COICP-INT-001
Release candidate expected later LMU-COICP-RC-001
Downstream release posture Internal engineering review only
Planned downstream review environment LMU-COICP Internal Engineering Review Environment
Planned downstream dataset Spring Semester Synthetic Incident Dataset
Planned downstream synthetic records 421
Planned downstream reviewer accounts 24
Planned downstream review window March 18–22, 2026
AI Incident Summary Deferred / disabled
Operational pilot Not approved

Review information

Field Value
Review Date Initial ES-102 review
Reviewers Product Owner, Product Engineer, ARB chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison, Facilities reviewer, Residence Life reviewer
Requirements Version LMU-COICP-REQ-001
Review Type Team review
Source Baseline Accepted ES-101 Vision package
Review Decision Accepted with carried-forward actions

Scenario coverage review

Scenario Requirements Coverage Finding
COICP-SYN-001 create synthetic incident, initial owner/status, creation evidence sufficient for Planning
COICP-SYN-118 owner change, handoff note, status update, evidence history, future review highest evidence-risk scenario
COICP-SYN-204 scenario-scoped access and denied export role matrix must be planned
COICP-SYN-219 status transition and closure rationale transition table must be designed
COICP-SYN-322 block/redirect emergency-related input Campus Safety wording needed
COICP-SYN-407 optional IT ownership extension keep scoped to coordination, not ITSM

Review checklist

  • [x] Requirements align with ES-101 Vision evidence.
  • [x] Requirements are scenario-specific.
  • [x] Functional requirements define realistic university behavior.
  • [x] Non-functional requirements are tied to scenario risks.
  • [x] Constraints preserve internal-review-only scope.
  • [x] Use cases use concrete LMU scenarios.
  • [x] Traceability connects scenarios to downstream stages.
  • [x] AI Incident Summary is disabled through RC-001.
  • [x] Emergency-boundary behavior is explicit.
  • [x] Role-scoped access is explicit.
  • [x] Prohibited behaviors remain visible.
  • [x] Planning handoff is clear.

Review findings

ID Finding Severity Scenario Action Owner Status
RRF-001 Six-scenario set is accepted but must remain stable through Planning and Architecture. Medium all Freeze scenario set for ES-103 handoff. Product Owner Open
RRF-002 Handoff evidence for COICP-SYN-118 is the primary auditability risk. High COICP-SYN-118 Plan evidence model and failure behavior. ARB chair / Product Engineer Open
RRF-003 Role-scoped access for Residence Life requires explicit matrix. High COICP-SYN-204 Create planning and architecture dependency. IT security reviewer Open
RRF-004 AI Incident Summary must remain disabled. Medium all Carry disabled decision through Planning and Release. AI reviewer Open
RRF-005 Emergency-boundary wording needs Campus Safety review. Medium COICP-SYN-322 Carry wording and block/redirect behavior forward. Campus Safety liaison Open
RRF-006 Status transition table must be defined for HVAC closure. Medium COICP-SYN-219 Carry to Design. Product Engineer / Facilities reviewer Open
RRF-007 Synthetic-data cleanup procedure remains unresolved. Medium all Carry to Operations/Governance. Compliance reviewer Open
RRF-008 COICP-SYN-407 must not expand COICP into ITSM. Medium COICP-SYN-407 Keep as optional ownership/handoff extension. Product Owner / IT security reviewer Open

Review decision

Accepted with carried-forward actions.

The ES-102 requirements package is sufficiently concrete to begin ES-103 Planning. It gives Planning a clear scenario set, realistic university business problems, required behaviors, trustworthiness targets, constraints, use cases, traceability, and unresolved issues.

Conditions on acceptance

Planning may begin, but these items must not be treated as finalized:

  • exact status transition table;
  • exact role matrix;
  • emergency-boundary warning language;
  • retention and cleanup procedure;
  • review package/export implementation scope;
  • accessibility standard;
  • March 18–22 availability target;
  • any AI enablement.

Continue to Requirements Readiness Summary

Summarize the ES-102 package and hand the scenario set to Planning.

Open Readiness Summary →