Milestones
LMU/COICP Example
Milestones Example
Build the LMU/COICP planning baseline around concrete scenarios that flow into Architecture and later stages.
ES-103
Milestones
Readiness Points
Example purpose
This artifact is part of the ES-103 — Planning package for the LMU Campus Operations and Incident Coordination Platform. It keeps planning tied to realistic LMU business problems rather than generic categories.
Project
LMU Campus Operations and Incident Coordination Platform
Document control
| Field |
Value |
| Artifact owner |
COICP Product Engineer |
| Primary reviewers |
COICP Product Owner, Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison |
| Status |
Accepted for ES-103 planning baseline |
| Last updated |
2026-07-06 |
| Related Engineering Stage |
ES-103 — Planning |
| Project workspace target |
docs/project-workspace/planning/milestones.md |
Planning context
| Field |
Value |
| Source requirements package |
ES-102 — Requirements and Constraints |
| Planning baseline produced |
LMU-COICP-PLAN-001 |
| Architecture baseline expected next |
LMU-COICP-ARCH-001 |
| Design baseline expected later |
LMU-COICP-DES-001 |
| Implementation baseline expected later |
LMU-COICP-IMPL-001 |
| Integrated baseline expected later |
LMU-COICP-INT-001 |
| Release candidate expected later |
LMU-COICP-RC-001 |
| Downstream release posture |
Internal engineering review only |
| Planned downstream review environment |
LMU-COICP Internal Engineering Review Environment |
| Planned downstream dataset |
Spring Semester Synthetic Incident Dataset |
| Planned downstream synthetic records |
421 |
| Planned downstream reviewer accounts |
24 |
| Planned downstream review window |
March 18–22, 2026 |
| AI Incident Summary |
Deferred / disabled |
| Operational pilot |
Not approved |
Milestone register
| ID |
Milestone |
Readiness Evidence |
Scenario Driver |
Owner |
Status |
| M-001 |
Scenario set locked |
COICP-SYN-001, 118, 204, 219, 322, 407 selected and bounded |
all |
COICP Product Owner |
Planned |
| M-002 |
Intake/handoff planning complete |
COICP-SYN-001 and 118 workflow inputs documented |
COICP-SYN-001 / 118 |
COICP Product Engineer |
Planned |
| M-003 |
Evidence model inputs ready |
creation, owner change, status change, handoff, closure, and scope-warning evidence identified |
COICP-SYN-001 / 118 / 219 / 322 |
ARB chair |
Planned |
| M-004 |
Role-scope planning complete |
reviewer groups and allowed/denied actions drafted |
COICP-SYN-204 |
IT security reviewer |
Planned |
| M-005 |
AI disablement decision recorded |
AI Incident Summary deferred/disabled through RC-001 |
all |
AI reviewer / Product Owner |
Planned |
| M-006 |
Emergency-boundary planning complete |
COICP-SYN-322 block/redirect ownership assigned |
COICP-SYN-322 |
Campus Safety liaison |
Planned |
| M-007 |
Synthetic-data and retention boundary visible |
Spring Semester Synthetic Incident Dataset and retention uncertainty recorded |
all |
Compliance reviewer |
Planned |
| M-008 |
Internal-review assumptions documented |
24 reviewer accounts, 421 records, March 18–22 review window |
all |
IT security reviewer / Product Owner |
Planned |
| M-009 |
Architecture handoff ready |
ES-104 inputs summarized and reviewed |
all |
ARB chair |
Planned |