Record the LMU/COICP RC-001 release-readiness review, checklist, findings, actions, owners, decision, and ES-111 Operational Readiness handoff.

ES-110 Review LMU Release Findings

Example purpose

This artifact records the ES-110 release-readiness review meeting for LMU-COICP-RC-001.

The review confirms that the decision, conditions, scope, guardrails, AI status, risks, and ES-111 handoff are clear.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner LMU COICP Product Owner
Primary reviewers Product Engineer, Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison
Status LMU internal engineering review only; operational pilot blocked
Last updated 2026-07-06
Related Engineering Stage ES-110 — Release Readiness
Project workspace target docs/project-workspace/release/release_readiness_review.md

Review information

Field Value
Review Date March 17, 2026
Candidate LMU-COICP-RC-001
Planned deployment DEP-LMU-COICP-2026-03-18-001
Planned review environment LMU-COICP Internal Engineering Review Environment
Planned dataset Spring Semester Synthetic Incident Dataset
Review Decision Internal engineering review only; operational pilot blocked

Review checklist

  • [x] RC-001 identified.
  • [x] Evidence indexed.
  • [x] Defects assessed.
  • [x] Risks assessed.
  • [x] Guardrails reviewed.
  • [x] AI Incident Summary disabled.
  • [x] Release scope defined.
  • [x] Conditions documented.
  • [x] Decision authority identified.
  • [x] ES-111 readiness considered.
  • [x] Operational pilot explicitly blocked.
  • [x] Real data use explicitly prohibited.
  • [x] Synthetic dataset condition established.
  • [x] Campus Safety boundary concern carried forward.

Findings

ID Finding Severity Action Owner Status
RRF-001 Evidence write failure behavior blocks operational pilot. High Verify and retest. Architecture Review Board chair Open
RRF-002 Access-control matrix testing incomplete. Medium Complete before real-user pilot. IT Security Reviewer Open
RRF-003 Invalid status transition defect open. Medium Fix and retest. Product Engineer Open
RRF-004 AI Incident Summary disabled and should remain out of release scope. Low Keep disabled. AI Reviewer Closed
RRF-005 LMU internal engineering review can proceed with synthetic data. Low Apply release conditions. Product Owner Closed
RRF-006 Emergency-boundary testing should be formalized before pilot. Medium Complete focused test with Campus Safety. Product Engineer / Campus Safety liaison Open
RRF-007 Build/test command evidence should be finalized. Medium Add concrete command evidence. Product Engineer Open
RRF-008 Retention remains unresolved. Medium Prohibit production/sensitive data. Compliance Reviewer Open
RRF-009 ES-111 must prepare only review support, not real operations. Medium Preserve boundary in operations package. Product Owner Open

Review decision

Approved for LMU internal engineering review only.
Operational pilot is blocked.

ES-111 readiness consideration

ES-111 Operational Readiness may begin only for the approved internal engineering review scope.

ES-111 must prepare:

  • reviewer support model;
  • synthetic dataset controls;
  • monitoring signals;
  • incident response;
  • rollback and stop criteria;
  • reviewer transition message;
  • operational risk register.

ES-111 must not prepare production operations, real-user pilot operations, or real incident workflows until release-blocking defects are resolved and ES-110 is repeated.

Review conclusion

The release-readiness review is complete and supports a conditional handoff to ES-111.

The handoff is narrow: prepare controlled LMU internal review support, not operational pilot readiness.