Record the LMU/COICP operational-readiness review for RC-001, including reviewer groups, checklist, findings, deployment conditions, open risks, and decision for ES-112.

ES-111 Review LMU Operational Gate

Example purpose

This artifact records the ES-111 operational-readiness review for LMU-COICP-RC-001.

The review determines whether ES-112 Deployment and Transition may begin for the internal engineering review scope only.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner LMU COICP Product Owner
Primary reviewers Campus Operations lead, IT security reviewer, AI reviewer, Compliance reviewer, Architecture Review Board chair, Campus Safety liaison
Status Conditionally ready for ES-112 internal-review deployment
Last updated 2026-07-06
Related Engineering Stage ES-111 — Operational Readiness
Project workspace target docs/project-workspace/operations/operational_readiness_review.md

Review information

Field Value
Review Date March 17, 2026
Candidate LMU-COICP-RC-001
Planned deployment DEP-LMU-COICP-2026-03-18-001
Planned environment LMU-COICP Internal Engineering Review Environment
Planned dataset Spring Semester Synthetic Incident Dataset
Review Decision Conditionally ready for ES-112 deployment
Operational pilot Blocked

Review checklist

  • [x] ES-110 release boundary preserved.
  • [x] Approved LMU reviewer groups identified.
  • [x] Spring Semester Synthetic Incident Dataset identified.
  • [x] AI Incident Summary remains disabled.
  • [x] Support owners assigned.
  • [x] Monitoring signals defined.
  • [x] Incident response path defined.
  • [x] Stop criteria defined.
  • [x] Reviewer transition message drafted.
  • [x] Operational risks assigned.
  • [x] Known defects disclosed.
  • [x] ES-112 deployment conditions defined.
  • [x] Operational pilot remains blocked.
  • [x] Real and sensitive data remain prohibited.

Findings

ID Finding Severity Action Owner Status
ORF-001 Operational scope correctly limited to LMU internal engineering review. Low Preserve in deployment. Product Owner Closed
ORF-002 Reviewer groups are realistic and sufficient for review. Low Provision only approved accounts. IT Security Reviewer Closed
ORF-003 Spring Semester Synthetic Incident Dataset is required for meaningful LMU review. Medium Load dataset in ES-112. Product Engineer / Compliance Open
ORF-004 Stop criteria are necessary because guardrail-sensitive defects remain. High Include stop criteria in deployment transition. Architecture Review Board Open
ORF-005 AI-disabled status must be checked before access. Medium Include AI check in ES-112. AI Reviewer Open
ORF-006 Emergency-boundary scenario must be included. Medium Include COICP-SYN-322. Campus Safety Liaison Open
ORF-007 Access removal and dataset reset must be validated. Medium Validate rollback controls in ES-112. Product Engineer / IT Open
ORF-008 Known defects must remain visible during review. Medium Include defect list in transition message. Product Owner Open

Conditions on ES-112

ES-112 must:

  • deploy only LMU-COICP-RC-001;
  • use the Internal Engineering Review Environment;
  • provision only 24 approved reviewer accounts;
  • load only the Spring Semester Synthetic Incident Dataset;
  • keep AI Incident Summary disabled;
  • include COICP-SYN-322 emergency-boundary scenario;
  • validate reviewer account removal;
  • validate synthetic dataset reset;
  • deliver transition communication before access;
  • preserve all known defects.

Review decision

Conditionally ready for ES-112 Deployment and Transition for LMU internal engineering review only.

Operational pilot remains blocked.

Continue to Operational Readiness Summary