Risk Register

LMU/COICP Example

Risk Register Example

Build the LMU/COICP planning baseline around concrete scenarios that flow into Architecture and later stages.

ES-103 Risks Planning Control

Example purpose

This artifact is part of the ES-103 — Planning package for the LMU Campus Operations and Incident Coordination Platform. It keeps planning tied to realistic LMU business problems rather than generic categories.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner COICP Product Engineer
Primary reviewers COICP Product Owner, Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison
Status Accepted for ES-103 planning baseline
Last updated 2026-07-06
Related Engineering Stage ES-103 — Planning
Project workspace target docs/project-workspace/planning/risk_register.md

Planning context

Field Value
Source requirements package ES-102 — Requirements and Constraints
Planning baseline produced LMU-COICP-PLAN-001
Architecture baseline expected next LMU-COICP-ARCH-001
Design baseline expected later LMU-COICP-DES-001
Implementation baseline expected later LMU-COICP-IMPL-001
Integrated baseline expected later LMU-COICP-INT-001
Release candidate expected later LMU-COICP-RC-001
Downstream release posture Internal engineering review only
Planned downstream review environment LMU-COICP Internal Engineering Review Environment
Planned downstream dataset Spring Semester Synthetic Incident Dataset
Planned downstream synthetic records 421
Planned downstream reviewer accounts 24
Planned downstream review window March 18–22, 2026
AI Incident Summary Deferred / disabled
Operational pilot Not approved

Risk register

ID Risk Scenario Driver Likelihood Impact Mitigation Owner Downstream Mapping Status
R-001 Scenario set becomes generic or too broad. all Medium High Lock six COICP-SYN scenario threads. Product Owner Architecture scenario set Open
R-002 Handoff evidence is under-planned. COICP-SYN-118 Medium High Treat handoff evidence as architecture-critical. ARB chair DEF-003 if unverified Open
R-003 Role-scoped access remains vague. COICP-SYN-204 Medium High Define allowed/denied actions by scenario. IT security reviewer DEF-002 if incomplete Open
R-004 Status transition rules are weak. COICP-SYN-219 Medium Medium Carry status table into Design and Testing. Product Engineer DEF-001 if inconsistent Open
R-005 Emergency-boundary guidance is unclear. COICP-SYN-322 Medium High Assign Campus Safety liaison and block/redirect requirement. Campus Safety liaison DEF-004 if untested Open
R-006 AI Incident Summary creeps back into RC-001. all Medium High Record AI deferred/disabled decision. AI reviewer release/governance blocker Open
R-007 Synthetic data boundary is weakened. all Low High Use Spring Semester Synthetic Incident Dataset only. Compliance reviewer operations/governance risk Open
R-008 Internal review is mistaken for operational pilot. all Medium High Repeat internal-review-only posture in every stage. Product Owner release/deployment boundary Open
R-009 Evidence write failure is not planned. COICP-SYN-118 / 219 Medium High Carry fail-safe behavior into Architecture and Design. ARB chair DEF-003 Open
R-010 Review/export over-discloses records. COICP-SYN-118 / 204 Medium Medium Defer full export until access/evidence stable. IT security reviewer / ARB chair future test risk Open
R-011 Support model is vague for March 18–22 review. all Medium Medium Define review-window support assumptions. IT operations representative operations/readiness risk Open

Continue to Dependency Map

Move to the next planning artifact while preserving the same LMU scenario-driven flow.

Open Dependency Map →