Integration Decision Record

LMU/COICP Example

Integration Decision Record Example

Record the LMU/COICP integration decision for LMU-COICP-INT-001, including rationale, integrated changes, required follow-up, risks accepted, approvals, and testing handoff.

ES-108 Decision Integration Gate

Example purpose

This artifact records the ES-108 integration decision.

The decision determines whether the reviewed implementation increment can be integrated into the shared baseline and handed to ES-109 Testing and Verification.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner COICP Product Engineer
Primary reviewers Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison
Status Accepted with follow-up
Last updated 2026-07-06
Related Engineering Stage ES-108 — Integration
Project workspace target docs/project-workspace/integration/integration_decision_record.md

Integration context

Field Value
Integrated baseline LMU-COICP-INT-001
Candidate expected after testing LMU-COICP-RC-001
Integration decision posture Accepted with follow-up
Target testing posture Internal engineering review candidate only
Planned review environment LMU-COICP Internal Engineering Review Environment
Planned dataset for downstream review Spring Semester Synthetic Incident Dataset
Planned synthetic records 421
Planned reviewer accounts 24
Planned review window March 18–22, 2026
AI Incident Summary Deferred / disabled
Operational pilot Not approved

Decision

Accepted with follow-up as LMU-COICP-INT-001.

Decision rationale

The core implementation increment is traceable to LMU requirements and design, preserves major guardrails on normal paths, and provides enough evidence to support integration into the shared baseline.

Several verification gaps remain, but they are visible, assigned, and appropriate to carry into ES-109 Testing and Verification.

Integrated changes

  • IncidentRecord entity.
  • EvidenceEvent entity.
  • Create synthetic incident workflow.
  • Partial status and handoff update workflow.
  • Basic access-control checks.
  • Initial validation and error behavior.
  • AI Incident Summary deferment.
  • No real incident workflow.
  • No production or emergency workflow.

Required follow-up

Follow-Up Owner Target Stage Downstream Mapping
Add access-control matrix tests. IT security reviewer ES-109 DEF-002
Add invalid status transition tests. Product Engineer ES-109 DEF-001
Test evidence write failure behavior. Architecture Review Board chair / Product Engineer ES-109 DEF-003
Formalize emergency-boundary test with Campus Safety. Product Engineer / Campus Safety liaison ES-109 DEF-004
Finalize build/test command evidence. Product Engineer ES-109 DEF-005
Carry retention uncertainty forward. Compliance reviewer ES-110 / Governance Release/governance risk
Preserve AI Incident Summary deferment. AI reviewer ES-109 and ES-110 AI disabled

Risks accepted

Risk Acceptance Rationale Future Treatment
Access-control coverage incomplete. Basic checks exist; matrix testing is assigned. ES-109
Status transition validation incomplete. Gap is visible and assigned. ES-109
Evidence failure behavior not fully tested. High-severity finding carried forward. ES-109 and ES-110
Emergency-boundary behavior incomplete. No emergency workflow is released. ES-109
Retention rules unresolved. No retention assumptions hard-coded; no real data in scope. ES-110 / Governance
Build/test command evidence incomplete. Integration is conditional; formalization assigned. ES-109

Approval

Role Decision
COICP Product Engineer Approve with follow-up
Architecture Review Board chair Approve with evidence failure follow-up
IT security reviewer Approve with access-control follow-up
AI reviewer Approve with AI Incident Summary deferred
Compliance reviewer Approve with retention follow-up
Campus Safety liaison Approve with emergency-boundary follow-up

Decision boundary

This is an integration decision, not a release decision.

LMU-COICP-INT-001 is ready for ES-109 testing. It is not ready for release, internal engineering review, deployment, or pilot until ES-109 and ES-110 evaluate the remaining findings.

Continue to Integration Readiness Summary

Summarize integrated work, remaining risks, testing focus, and readiness for ES-109.

Open Integration Readiness Summary →