Release Decision Record¶
Example purpose¶
This artifact records the ES-110 release decision for LMU-COICP-RC-001.
The decision is deliberately limited. It allows controlled LMU internal engineering review while blocking operational pilot use.
Project¶
LMU Campus Operations and Incident Coordination Platform
Document control¶
| Field | Value |
|---|---|
| Artifact owner | LMU COICP Product Owner |
| Primary reviewers | Product Engineer, Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison |
| Status | Approved for LMU internal engineering review only |
| Last updated | 2026-07-06 |
| Related Engineering Stage | ES-110 — Release Readiness |
| Project workspace target | docs/project-workspace/release/release_decision_record.md |
Candidate context¶
| Field | Value |
|---|---|
| Candidate | LMU-COICP-RC-001 |
| Planned deployment ID | DEP-LMU-COICP-2026-03-18-001 |
| Planned review environment | LMU-COICP Internal Engineering Review Environment |
| Planned dataset | Spring Semester Synthetic Incident Dataset |
| Planned synthetic records | 421 |
| Planned reviewer accounts | 24 |
| Planned review window | March 18–22, 2026 |
| AI Incident Summary | Disabled |
| Operational pilot | Not approved |
Decision¶
LMU-COICP-RC-001 is not ready for operational pilot.
Approved only for LMU internal engineering review using the Spring Semester Synthetic Incident Dataset.
Decision rationale¶
Testing evidence shows that core workflow behavior exists and several normal-path checks pass.
However, release-sensitive defects remain open:
- evidence write failure behavior is unverified;
- access-control matrix testing is incomplete;
- invalid status transition validation has a known defect;
- emergency-boundary test is not fully formalized;
- build/test command evidence is incomplete.
These issues block operational pilot because they affect auditability, access control, workflow integrity, safety boundary, and repeatable verification.
Evidence considered¶
docs/project-workspace/testing/testing_readiness_summary.mddocs/project-workspace/testing/defect_log.mddocs/project-workspace/testing/guardrail_verification.mddocs/project-workspace/testing/ai_verification_record.mddocs/project-workspace/integration/integration_readiness_summary.mddocs/project-workspace/release/release_evidence_index.mddocs/project-workspace/release/defect_and_risk_assessment.mddocs/project-workspace/release/guardrail_release_review.mddocs/project-workspace/release/ai_release_review.mddocs/project-workspace/release/release_scope.mddocs/project-workspace/release/release_conditions.md
Risks accepted¶
| Risk | Accepted Only Under These Conditions |
|---|---|
| Internal engineering review may proceed despite incomplete verification. | Spring Semester Synthetic Incident Dataset only; 24 approved reviewer accounts only. |
| Retention uncertainty remains. | No production or sensitive records. |
| Access-control matrix incomplete. | No real users; approved reviewer accounts only. |
| Status validation defect open. | No operational workflow use. |
| Evidence write failure behavior unverified. | No operational pilot; no real incident records. |
| Emergency-boundary testing incomplete. | Synthetic Campus Safety scenario only; no emergency workflow. |
| AI workflow deferred. | AI Incident Summary disabled and out of scope. |
Required follow-up¶
- Resolve DEF-003 evidence write failure verification.
- Complete access-control matrix testing.
- Fix and retest invalid status transition validation.
- Formalize emergency/prohibited category testing.
- Finalize build/test command evidence.
- Maintain AI Incident Summary as disabled.
- Reassess release readiness after defects are addressed.
- Repeat ES-110 before any operational pilot.
Decision authority¶
| Role | Decision |
|---|---|
| LMU COICP Product Owner | Approve internal review only |
| Architecture Review Board chair | Block operational pilot |
| IT Security Reviewer | Block real-user pilot pending access tests |
| AI Reviewer | Approve with AI Incident Summary disabled |
| Compliance Reviewer | Approve synthetic data only |
| Campus Safety Liaison | Require emergency-boundary scenario before deployment and formal test before pilot |
| Product Engineer | Accept engineering follow-up |
Decision boundary¶
This is not an operational release.
The approved activity is LMU internal engineering review only. ES-111 Operational Readiness may begin only for supporting that internal review scope.