Work Breakdown Structure

LMU/COICP Example

Work Breakdown Structure Example

Build the LMU/COICP planning baseline around concrete scenarios that flow into Architecture and later stages.

ES-103 Work Packages Execution Structure

Example purpose

This artifact is part of the ES-103 — Planning package for the LMU Campus Operations and Incident Coordination Platform. It keeps planning tied to realistic LMU business problems rather than generic categories.

Project

LMU Campus Operations and Incident Coordination Platform

Document control

Field Value
Artifact owner COICP Product Engineer
Primary reviewers COICP Product Owner, Architecture Review Board chair, IT security reviewer, AI reviewer, Compliance reviewer, Campus Safety liaison
Status Accepted for ES-103 planning baseline
Last updated 2026-07-06
Related Engineering Stage ES-103 — Planning
Project workspace target docs/project-workspace/planning/work_breakdown_structure.md

Planning context

Field Value
Source requirements package ES-102 — Requirements and Constraints
Planning baseline produced LMU-COICP-PLAN-001
Architecture baseline expected next LMU-COICP-ARCH-001
Design baseline expected later LMU-COICP-DES-001
Implementation baseline expected later LMU-COICP-IMPL-001
Integrated baseline expected later LMU-COICP-INT-001
Release candidate expected later LMU-COICP-RC-001
Downstream release posture Internal engineering review only
Planned downstream review environment LMU-COICP Internal Engineering Review Environment
Planned downstream dataset Spring Semester Synthetic Incident Dataset
Planned downstream synthetic records 421
Planned downstream reviewer accounts 24
Planned downstream review window March 18–22, 2026
AI Incident Summary Deferred / disabled
Operational pilot Not approved

Work packages

ID Work Package Scenario Driver Description Owner Dependencies Evidence Produced Estimate Status
WP-001 Scenario set baseline all COICP-SYN scenarios Lock the six synthetic scenario threads for Architecture. COICP Product Owner Requirements baseline scenario decision record 1–2 hours Planned
WP-002 Intake workflow planning COICP-SYN-001 Define create record, required fields, and creation evidence. COICP Product Engineer WP-001 create workflow input 1–2 hours Planned
WP-003 Handoff/evidence planning COICP-SYN-118 Define owner change, status change, handoff note, and evidence needs. Architecture Review Board chair / Product Engineer WP-001, WP-002 evidence model input Half day Planned
WP-004 Scenario-scoped role model COICP-SYN-204 Define Residence Life, Facilities, Campus Operations, ARB, Compliance, AI, and IT reviewer access. IT security reviewer WP-001 role matrix input Half day Planned
WP-005 Status and closure planning COICP-SYN-219 Define status progression, invalid transition concern, and closure rationale need. COICP Product Engineer WP-003 status/closure planning note 1–2 hours Planned
WP-006 Emergency-boundary planning COICP-SYN-322 Define block/redirect behavior and wording owner for emergency-related entries. Campus Safety liaison / Product Owner WP-001 boundary guidance input 1–2 hours Planned
WP-007 Optional IT handoff extension COICP-SYN-407 Decide whether Wi-Fi disruption ownership is first-baseline or extension only. COICP Product Owner / IT security reviewer WP-004 extension decision note 30–60 minutes Planned
WP-008 AI disablement decision all scenarios Confirm AI Incident Summary is deferred/disabled through RC-001. AI reviewer / Product Owner WP-001 AI deferment note 1–2 hours Planned
WP-009 Synthetic-data and retention review all scenarios Confirm synthetic-only boundary and no hard-coded retention rule. Compliance reviewer WP-001, WP-003 compliance planning note Half day Planned
WP-010 Reviewability planning COICP-SYN-118 Identify future Architecture Review Board review package needs without overbuilding export. ARB chair / Product Engineer WP-003 review package input 1–2 hours Planned
WP-011 Architecture handoff package all scenarios Convert planning decisions into ES-104 architecture inputs. Architecture Review Board chair WP-001–WP-010 planning readiness summary 1–2 hours Planned
WP-012 Internal-review operations assumptions all scenarios Define March 18–22 review window, 24 reviewers, support path, and availability expectations. IT security reviewer / Product Owner WP-001 operations planning input 1–2 hours Planned

Deferred work

  • operational pilot planning;
  • production rollout;
  • real campus incident integration;
  • AI Incident Summary implementation;
  • automated trend detection;
  • full review/export implementation;
  • public-facing incident portal;
  • enterprise ITSM replacement;
  • emergency dispatch or notification integration.